Work on Foresthill Bridge To Increase

Work on the Foresthill Bridge Seismic Retrofit and Repainting Project will increase as the contractor, Golden State Bridge, adds a second work shift beginning the week of June 6, 2011.

Current lane closures are allowed between the hours of 8 AM and 4 PM. However, from Memorial Day through Labor Day, lane closures are permitted from 8 AM until 12 noon on Fridays. With the second shift, lane closures at night are allowed from Sunday night at 6 PM through 7 AM Friday.

For additional information, please visit the project website:http://foresthillbridgerenewal.com/